Severn Trent are doing some vital improvement work on Hucclecote Road, investigation work is planned from 14th December 2019 for approximately nine days.

Important things to know:
Phase 1 (14/12/19 – 22/12/19) – Initially they plan to carry out investigation work at the junction of Hucclecote Road and Churchdown Lane. Four way traffic lights will be in place at the junction and they will be manually controlled between 0700hrs – 1900hrs.

Phase 2 (06/01/20 – 07/02/20)- In January they will return to install a new water main and valves, this will take place in the grass verge opposite the Church using signs and barriers.

Phase 3 (10/02/20 – 14/02/20) – Final connections onto the existing water main will involve four way lights in place again.
Please note these dates may be subject to change.

0800 521 660 – Amey 24hr Customer Service Centre
0800 783 4444 – Severn Trent Customer Operations Service Centre

 

Project reference – 6138861